U.S. Sen. Ron Wyden, D-Ore., demanded an investigation into the contracting practices at the Department of Energy’s Hanford nuclear site in Washington State and blasted the DOE for its lack of oversight, citing an internal report from a project management contractor obtained earlier this year.
The report from Bechtel National, Inc., dated January 9, 2015, shows that about $277 million of taxpayer money has been spent on work orders that have not been completed at the Hanford Waste Treatment Plant. It also shows that it is costing roughly $5.3 million a year to keep the contracts in place for just one portion of the plant known as the Pretreatment Plant. The Waste Treatment Plant is years behind schedule and billions of dollars over budget. Work on the Pretreatment Plant has been halted since 2012 because of unresolved design and construction problems.
In a letter on Tuesday, Wyden asked Department of Energy Inspector General Greg Friedman to investigate Bechtel’s activities at the Hanford site and what role the DOE played in potential mismanagement of taxpayer funds.
“The DOE has been mismanaging the cleanup at Hanford for three decades,” Wyden said. “I am outraged that the Department claims it doesn’t have enough money to clean up Hanford yet allows such an egregious waste of taxpayer dollars. Taxpayers deserve to know how their money has been spent and the citizens of the Pacific Northwest deserve to have this place cleaned up.”